Construction Law

Construction Contracts in Türkiye: Eser Sözleşmesi Explained for Foreign Investors

If you are building, renovating or commissioning any work in Türkiye, your relationship with the contractor is usually a works contract, called eser sözleşmesi in Turkish and governed by the Turkish Code of Obligations No. 6098. In plain terms, the contractor promises to deliver a finished result, a building, a fit-out, an engineering work or a software build, and you promise to pay an agreed price. This guide explains the parts that most often cause disputes for foreign investors: how the price is set, when the work must be delivered, what happens if it is defective or late, and how either side can end the contract.

What an eser sözleşmesi actually is

An eser sözleşmesi (works contract, sometimes translated as contract for work) is the agreement under which a contractor undertakes to produce a specific result, and the client undertakes to pay for it. It is the standard legal frame for construction, renovation, turnkey fit-outs, manufacturing of a bespoke item, and many engineering or technical works.

The key word is result. Unlike an ordinary service or employment relationship, where someone is paid for their effort and time, in a works contract the contractor owes you a finished, usable work. If the result is not delivered, or is delivered defective, the contractor is in breach even if they worked hard.

The works contract is regulated in the special-contracts part of the Turkish Code of Obligations No. 6098. The provisions cover the contractor's duties, the price, defect liability, and termination. Exact article numbers should be confirmed against the current text of Law No. 6098 before you rely on any single citation.

Two parties sit at the centre of every works contract: the yüklenici (contractor, the party who builds or produces) and the iş sahibi (the client or employer, the party who orders and pays). Throughout this guide, "you" means the client.

Which of these is your situation?

Notify the contractor in writing without undue delay, and keep the notice. Depending on how serious the defect is and whether the contractor was at fault, you can generally require repair, ask for a proportionate price reduction, reject the work if it cannot reasonably be accepted, or claim damages. Latent defects can be raised when they come to light, provided you notify promptly on discovery. The limitation clock runs from delivery: two years for movable works, five years for buildings, twenty years for gross fault.
Check first whether your contract has a penalty clause (cezai sart). If it does, you claim the agreed daily or weekly sum without having to prove your exact loss. If it does not, you fall back on general default rules and must show the damage the delay actually caused. A Turkish court can reduce a penalty it finds excessive, but a paying party that is a merchant (tacir) generally cannot ask for that reduction, save in narrow cases where the penalty would be ruinous.
Under a lump-sum (goturu bedel) contract the contractor must in principle complete the agreed scope for the agreed figure, even if it costs them more. There is a narrow exception where extraordinary, unforeseeable circumstances make performance excessively difficult, and it is heavily fact-dependent. In practice most price arguments are really scope arguments, so check what the drawings and specifications actually cover before treating a demand as a variation.
As a general rule you may terminate before completion, but you must pay for the work already done and compensate the contractor, with their saved expenses and alternative earnings taken into account. Walking away early is possible, but it is not free. If the reason is the contractor's own breach, you are in a stronger position: warn them, set a reasonable deadline to put the work right, and act if they fail.

The contractor's core duties

Turkish law expects the contractor to perform with care and loyalty, and to protect your interests as a careful professional would. In practice this breaks down into several duties:

  • Personal performance, in principle: the contractor is generally expected to carry out the work personally or under their own management. Subcontracting may be allowed, but the contractor stays responsible to you for the whole result.
  • Supplying materials of proper quality: where the contractor provides the materials, they must be suitable; where you supply them, the contractor must use them carefully and warn you if they are unfit.
  • Duty to warn: if your instructions, the supplied materials, or the ground or site conditions threaten the work, the contractor must warn you in time. A contractor who stays silent can become liable for the resulting damage.
  • Timely start and diligent progress: the contractor must begin and continue the work so that delivery on time is realistic.
For foreign investors, the duty to warn is one of the most useful protections in Turkish law. Insist that all warnings and instructions are exchanged in writing, by email or formal letter, so the record is clear if a dispute arises later.

Price: lump-sum (götürü) versus cost-basis (maliyet)

How you agree the price changes your risk profile dramatically. Turkish law recognises two main models.

1. Lump-sum / fixed price (götürü bedel). You agree a single total figure for the whole work. The headline benefit is certainty: in principle the contractor must complete the agreed work for that price, even if it turns out to cost them more, and even if it costs them less they cannot charge you more. This shifts most cost risk onto the contractor.

2. Cost-basis price (maliyet / approximate cost). The price is built up from the actual labour and materials, sometimes against an estimate. Here more of the cost risk sits with you, the client, because the final figure can move with real costs.

Even a fixed (götürü) price is not always absolutely frozen. Turkish law allows a limited adjustment of the price where, due to extraordinary circumstances that could not be foreseen, or that were excluded by the parties' assumptions, completing the work becomes excessively difficult. This is a narrow exception, not a routine escape from a bad bargain, and it is heavily fact-dependent. The precise statutory wording and threshold must be confirmed by a lawyer for your specific contract.

For most foreign investors who want budget certainty, a clearly scoped götürü bedel contract is attractive, but it only protects you if the scope, drawings and specifications are tightly defined. A vague scope turns every change into a "variation" the contractor will price separately.

Delivery, acceptance and inspection

When the work is finished, the contractor delivers it and you inspect and accept it. This moment matters because acceptance affects your rights over defects.

  • Inspect promptly. Once you receive the work, you are expected to examine it within a reasonable time, as far as the ordinary course of business allows, and to notify the contractor of any defects you find.
  • Notify defects in writing. If you discover a defect, tell the contractor without undue delay. Silence can be treated as acceptance of the work as it is.
  • Hidden defects. Defects that could not be seen on a normal inspection (latent defects) can be raised when they later come to light, provided you notify the contractor promptly once you discover them.
If you accept the work expressly or by conduct without reserving your rights, you can lose claims for defects that an ordinary inspection would have revealed. Do not sign an unconditional acceptance or final handover protocol until your own technical advisor has inspected the work.

A practical tool here is a snagging / acceptance protocol (a handover document listing outstanding items). Record every open defect in it and make payment of the final instalment conditional on those items being closed.

Defect liability (ayıba karşı tekeffül)

Ayıba karşı tekeffül means the contractor's liability for defects in the work, the Turkish equivalent of a statutory warranty for defects. If the delivered work does not have the agreed or expected qualities, or is unfit for its purpose, you generally have a menu of remedies.

  • Repair / rectification: you can require the contractor to fix the defect, typically at the contractor's cost, where this is possible and not disproportionately expensive.
  • Price reduction: you can ask for a reduction in the price proportionate to the loss of value caused by the defect.
  • Rescission / refusal of the work: if the defect is so serious that the work cannot reasonably be accepted, or accepting it cannot be expected of you, you may reject the work and unwind the contract.
  • Damages: separately, you may claim compensation for losses caused by the contractor's fault.
These defect remedies come from the works-contract provisions of the Turkish Code of Obligations No. 6098. Which remedy you can choose depends on how serious the defect is and whether the contractor was at fault. The exact article numbers for each remedy should be verified against the current statute.

Importantly, if the defect arose because the contractor ignored your instructions or used unsuitable materials they should have warned you about, that strengthens your position. If the defect is your fault, for example you imposed a design the contractor warned against, the contractor's liability can be reduced or excluded.

Common belief

A fixed price is a fixed price, so nothing can move it.

In fact

The general rule holds: under a lump-sum (goturu bedel) contract the contractor must complete the agreed scope for the agreed figure, even if it costs them more. But Turkish law allows a limited price adjustment where extraordinary circumstances that could not be foreseen make completing the work excessively difficult. It is a narrow, fact-dependent exception, not a routine way out of a bad bargain.

Common belief

A building comes with a long guarantee, so I can raise defects whenever I notice them.

In fact

Defect claims are subject to tiered limitation periods running from delivery: two years for ordinary movable works, five years for immovable structures, and twenty years where the contractor acted with gross fault. Deadlines run faster than most clients expect.

Common belief

Signing the handover protocol is just an administrative formality.

In fact

Acceptance matters. If you accept the work expressly or by conduct without reserving your rights, you can lose claims for defects that an ordinary inspection would have revealed. Inspect first, list every open item, and do not sign unconditionally.

Common belief

If I write a large enough delay penalty, the contractor has to pay it in full.

In fact

Turkish courts can reduce a penalty found to be excessive, so a realistic, capped figure tied to defined milestones is more enforceable than an aggressive one. Whether reduction is even available depends on the paying party's status: a merchant (tacir) generally cannot ask for it, save in narrow cases where the penalty would be ruinous.

Delay and penalty clauses (cezai şart)

Late delivery is one of the most common disputes on Turkish construction projects. There are two layers of protection.

1. Statutory consequences of delay. If the contractor is late, general default rules let you claim the damage the delay actually caused, and in serious cases give grounds to end the contract. You normally have to show the loss.

2. Contractual penalty clause (cezai şart / liquidated damages). A penalty clause is a pre-agreed sum the contractor must pay for each day or week of delay, regardless of proof of loss. This is usually the more powerful tool, because you do not have to prove your exact damages, you simply apply the agreed rate.

A well-drafted delay penalty is specific: it states the daily or weekly amount, a cap, the milestones it applies to, and whether you can also claim damages above the penalty. Tie the penalty to clearly defined completion milestones, not just a vague "end date".
Turkish courts can reduce a penalty that is found to be excessive, so a realistic, defensible figure is more enforceable than an aggressive one. There is an important exception, though: under the Turkish Commercial Code, a party that is a merchant (tacir) generally cannot ask the court to reduce an agreed penalty, except in narrow cases where the penalty would be ruinous. So whether the right to reduction is even available depends on whether the paying party is a merchant. This reflects the law as of 2026; confirm your own status and the current standard with your lawyer.

Termination before completion

Sometimes a project has to stop before the work is finished. Turkish law gives both sides exit routes, with different financial consequences.

  • Client's right to terminate against payment: as a general rule, the client may terminate the works contract before the work is completed, but in that case the client must pay for the work already done and compensate the contractor, with the contractor's saved expenses and what they earn (or deliberately fail to earn) elsewhere taken into account. In short, walking away early is possible but it is not free.
  • Termination for the contractor's breach: if it becomes clear during the work that, through the contractor's fault, the work will be defective or contrary to the contract, you can warn them, set a reasonable deadline to put it right, and if they fail, take steps including ending the contract or having the work corrected at their expense.
  • Impossibility and unforeseen events: if performance becomes impossible for reasons attributable to neither side, the contract can fall away, with a settlement for the work and costs incurred up to that point.
  • Death or incapacity of the contractor: where the contractor's personal skill was essential, their death or loss of capacity can end the contract.
These termination scenarios are set out in the works-contract provisions of the Turkish Code of Obligations No. 6098. The financial settlement on early termination is fact-sensitive; confirm the governing articles and the calculation method for your situation.

Contractor liability periods, and how to protect yourself

Defect claims under a works contract are subject to limitation periods, after which the claim can no longer be brought. Turkish law uses a tiered framework that depends, among other things, on whether the work is an immovable structure (a building) and on the contractor's degree of fault. The periods run from delivery of the work.

  • For ordinary movable works, the defect-liability claim runs out two years after delivery.
  • For defective immovable structures (buildings), a longer five-year period applies, reflecting how serious construction defects are and how late they can appear.
  • Where the contractor acted with gross fault (ağır kusur), the period extends to twenty years regardless of whether the work is movable or immovable.

These tiers come from the Turkish Code of Obligations No. 6098 (the works-contract limitation rule). A separate but related protection applies where the contractor deliberately concealed a defect (kasten gizleme): concealment stops the contractor from relying on your acceptance to escape liability for that hidden defect. In other words, gross fault is what stretches the limitation period to twenty years, while concealment is what defeats the argument that you lost your rights by accepting the work, two distinct ideas that are easy to confuse.

These periods (two years for movable works, five years for buildings, twenty years for gross fault) reflect the statute as of 2026; confirm the current figures and how they apply to your contract with a lawyer before you rely on a specific deadline. Do not assume your claim is still in time, deadlines run faster than most clients expect.

Practical steps that protect foreign investors:

  • Get the contract in writing, in Turkish or bilingual, with the Turkish version's status defined, and with the scope, drawings and specifications attached.
  • Use retention (teminat) and staged payments tied to milestones, so you keep leverage until defects are cleared.
  • Require performance and advance-payment guarantees (bank guarantees) for larger projects.
  • Document everything: warnings, instructions, variations, inspections and the handover protocol.
  • Act fast on defects and deadlines, and take legal advice early if delivery slips or quality drops.
6098LAW NO.
Turkish Code of Obligations (Turk Borclar Kanunu)

Contains the works-contract (eser sozlesmesi) provisions on the contractor's duties, the price, defect liability, termination and the tiered limitation periods. Confirm the exact article numbers against the current text of Law No. 6098 before relying on any single citation.

Turkish Commercial Code (Turk Ticaret Kanunu)

Source of the rule that a paying party which is a merchant (tacir) generally cannot ask a court to reduce an agreed penalty, except in narrow cases where the penalty would be ruinous.

Deadlines that decide a defect claim
2 yearsDefect claims on ordinary movable works, counted from delivery.
5 yearsDefect claims on buildings and other immovable structures, from delivery.
20 yearsApplies where the contractor acted with gross fault (agir kusur), movable or immovable.

What to gather before you speak to a lawyer

Most works-contract questions turn on dates and documents rather than argument. Put these together first so the position can be assessed quickly.

Frequently asked questions

What is an eser sözleşmesi in Turkish law?

It is a works contract under the Turkish Code of Obligations No. 6098, in which a contractor (yüklenici) undertakes to produce a defined result, such as a building, renovation or bespoke work, and the client (iş sahibi) undertakes to pay an agreed price. The contractor owes you a finished, usable result, not just their effort.

Is a fixed (götürü) price really fixed in Türkiye?

As a rule, yes: under a lump-sum (götürü bedel) contract the contractor must complete the agreed scope for the agreed price, even if it costs them more. There is a narrow legal exception that allows an adjustment where unforeseeable, extraordinary circumstances make performance excessively difficult, but it is hard to invoke and very fact-dependent. A clearly defined scope is what keeps the price firm.

What can I do if the construction work is defective?

Depending on how serious the defect is and whether the contractor was at fault, you can generally require repair, ask for a proportionate reduction in the price, reject the work and unwind the contract if it is unacceptable, and claim damages for losses caused by the contractor. Inspect promptly and notify defects in writing, because delay can cost you your rights.

How do delay penalties (cezai şart) work?

A penalty clause sets a pre-agreed amount the contractor pays for each period of delay, without you having to prove your exact loss. It is one of the strongest tools against late delivery. A Turkish court can reduce a penalty it finds excessive, so a realistic, well-capped figure tied to clear milestones is more enforceable. Note one caveat: under the Turkish Commercial Code a party that is a merchant (tacir) generally cannot ask the court to reduce an agreed penalty, so whether reduction is available depends on the paying party's status.

Can I cancel a construction contract before the work is finished?

Yes. As a general rule the client can terminate before completion, but you must pay for work already done and compensate the contractor, with their saved costs and alternative earnings taken into account. You also have stronger termination rights if the contractor's own breach means the work will be defective or contrary to the contract.

How long is the contractor liable for defects?

Turkish law uses tiered limitation periods running from delivery: as of 2026, two years for ordinary movable works, five years for immovable structures (buildings), and twenty years where the contractor acted with gross fault. Separately, deliberate concealment of a defect stops the contractor from relying on your acceptance to escape liability for that hidden defect. These figures reflect the current statute but should be confirmed by a lawyer for your specific case, because deadlines run faster than most clients expect.

Need a lawyer for this?We handle construction & zoning law for foreigners, end to end, in English, on a fixed fee.
Construction & Zoning Law

Related articles

Construction & Zoning Law in Türkiye: A <em>Practical Guide</em> for Foreign InvestorsFlat-for-Land (<em>Kat Karşılığı İnşaat</em>) Agreements in Türkiye: How the Landowner–Developer Swap Really Works
Let's begin

Speak to a Turkish lawyer who speaks your language.

Tell us your commercial, corporate or personal matter and get a clear, fixed-fee answer from a real Turkish lawyer — usually within one business day.

★★★★★ 4.9 from 60 Google reviews · Recognised on Mondaq, Clutch & Trustpilot
WhatsApp us
A real lawyer replies — usually within a day
WhatsAppEmailBook a consultation